154 kV Gaziantep GES Çörekli Substation Contract has been signed.

154 kV Gaziantep GES Çörekli Substation Contract has been signed.

The turnkey contract of 154 kV Çörekli Substation to be build in Gaziantep has been signed with Kalyon Enerji Yatırımları A.Ş on 01 December 2022.

Within the contract scope, Basic and Detailed Design, Equipment Supply, IEC 61850 based Automation system, Civil Work, Erection, Test and Commissioning of 2 pcs of 154/33 kV 20(25) MVA and 1 pcs 154/33 kV 10(12,5) MVA  Power Transformers, 3 pcs of 154 kV Transformer Feeders, 2 pcs of 154 kV Line Feeder, 1 pcs of Coupling Feeder and 11 pcs of 33 kV Medium Voltage Feeders to be completed on turn-key basis.

© 2022 GES Genel Elektrik Sistemleri Yapım ve Mühendislik A.Ş